TECHNICAL GUIDE

Planning a nodal seismic array: a field and data checklist

Prepare receiver, recording, timing, power and data-recovery requirements for a nodal seismic array, with documented field examples and a practical project brief.

SmartSolo Scientific · Published

Define the acquisition plan before ordering nodes

A useful array brief connects the scientific objective to the receiver layout, required channels, recording schedule and data workflow. Instrument quantity alone does not define a complete system. The checklist below is a starting point for discussion with the project geophysicist and instrument team.

EarthScope's node-use policy also treats planning, data handling, recharge and functional validation as linked parts of a nodal experiment. Its operational policy applies to its own fleet; use the SmartSolo team to confirm arrangements for your project.

Seven decisions to record in the project brief

Array requirements to agree before field deployment
DecisionRecord in the briefConfirm with the instrument team
Objective and methodResearch question, active or passive acquisition, target area and intended analysis.Required response, components and recording settings.
Receiver layoutStation count, proposed coordinates, spacing, access constraints and redeployments.Available configurations, installation accessories and field workflow.
Recording scheduleSample interval, start and stop times, continuous or scheduled recording, and total duration.Supported settings and usable storage for the chosen configuration.
Timing and station recordsTiming requirements, coordinates, station IDs, orientation and deployment/recovery records.GNSS configuration, timing checks and metadata export workflow.
Power and environmentExpected temperature, site conditions, access intervals and charging opportunities.Battery endurance at the requested settings and conditions.
Data recoveryDownload windows, computers, working storage, backup copies and destination data format.Required hardware/software and a trial download before deployment.
Logistics and supportCrew, training needs, spares, shipment dates and delivery location.Equipment availability, lead time and applicable support arrangements.

Estimate data volume with explicit assumptions

For an uncompressed payload estimate, multiply station count × recorded channels per station × samples per second × bytes per sample × recording seconds. This is a planning calculation, not a storage guarantee: headers, file structure, compression, auxiliary channels and usable device capacity can change the requirement. ADC bit depth does not by itself determine the saved bytes per sample.

Worked planning example

Assume 100 stations, 3 channels, 500 samples/second, 4 stored bytes/sample and 24 hours. The sample payload is 51,840,000,000 bytes: about 51.84 GB in decimal units, or 48.28 GiB. One station would generate about 0.5184 GB/day under those assumptions. Confirm the actual recording format and add capacity for the rest of the workflow.

Test one complete acquisition and recovery cycle

Before the main deployment, run a small trial using the intended instrument configuration and computers. Record configuration and station metadata, acquire a sample, download it, inspect the files in the planned analysis workflow and make a verified backup. Resolve format, timing and installation questions before scaling the process.

The IGU-BD3C-5 catalog endurance statement is “up to 30 days continuous” at 25 °C and 2 ms sampling. Preserve those conditions when comparing options; do not apply the same duration to every model, temperature or configuration.

Use documented projects as context

Each case identifies its project sources and scope. A previous deployment is evidence of that project, not a guarantee of performance in different field conditions.

Request the system configuration

Share the completed brief with the team, including quantities, recording settings, environmental conditions, data workflow and delivery dates. Ask for a current equipment list, compatible software and the relevant manuals before finalizing the deployment.

Explore the Large-N array application · Discuss an array project · Compare component and frequency options

Sources and product information

Product values are drawn from the linked SmartSolo catalog entries. Ask for the latest datasheet for the exact configuration. External sources provide technical background and do not imply endorsement of this guide.

Contact us about a technical detail.